Meet us at:
Midland Machinery Show
20th/21st November 2019
George Stephenson Exhibition Hall - Stand No 8
LAMMA 2020
7th/8th January 2020
Hall 8 - Stand 8.728
The Sentry Conference
5th February 2020
Confidence in our design,
materials and care in
manufacturing and installation
is reflected in our
10-year warranty.

of Flach & Le-Roy Ltd
Self Installation
How long does it take to install a drive-on-floor system and can I install it myself?Answer:
We offer a self-install package, including one-day’s on-site instruction and an installation manual, for both ducts and floors.
- Generally, the rate of floor installation is about 20 to 25 square metres per man/day so an 18 m x 18 m floor area should take around 16 man-days.
- A 20 m long x 3.0 m high duct will take around 10 man days to erect.
